Friday, July 21, 2017
New Bike Racks on Wiehle-Reston East Station Plaza
We've reported on the need for more free bike parking at the Wiehle-Reston East Metro station. The free bike room adjacent to the paid secure bike room fills up on most days and bikes end up being locked to various objects in the room. One was even hanging from the fence recently.
According to development plans (Sheet 11, page 177), bike racks will be placed on the plaza outside the station entrance. We're pleased to report that a new set of inverted U racks was recently installed near the bike share station. The racks are not covered but they do provide an option for overflow parking from the bike room. Thanks to Comstock and Fairfax County for working with us to install these racks.
![]() |
| Overflow bike parking at Wiehle station. Capacity is 36 bikes. There were 54 parked on July 12. |
![]() |
| New U racks on Wiehle Station Plaza |
![]() |
| Reston Station Development Plan, Sheet 11 showing proposed bike rack locations on plaza. |
Labels: comstock, wiehle station bike room, wiehle-reston east
Wednesday, July 17, 2013
Wiehle Ave Metrorail station bike room under construction
Today Fairfax County staff are installing bike racks and other equipment in the Wiehle Ave Metrorail station bike room that is part of the Reston Station development by Comstock. The room will have secure, card-accessed parking for approximately 240 bikes. There will be racks outside the bike room available to everyone. There will also be two Fixit stations similar to, if not the same as, the Fixit station made by Dero. The fee structure and card system for accessing the bike room have not been finalized.Here's a photo of some of the racks being installed today. The tall black racks will accommodate several bikes hung by their front wheel. The red U racks leaning against the will each hold 2 bikes and will be lined up around the room:
We just learned today that Phase I of the Dulles Rail project, which includes the Wiehle station, will be delayed by approximately eight weeks. The original start date for Metro service was late December. The delay pushes that date back at least until late February.
Labels: comstock, fixit station, wiehle station
Wednesday, May 22, 2013
Wiehle Ave trail closed near W&OD Trail
Due to construction related to the new Wiehle Ave Metro station, the trail on Wiehle Ave from the W&OD Trail to the Sunset Hills Road intersection is closed. Trail Closed signs have been in place for nearly two weeks but no work was being done. Last week I joined an onsite meeting with VDOT and county staff and the representative from the company doing the work, Comstock. Actually I butted into their meeting to explain why it was inconsiderate to block the trail for no apparent reason.| Wiehle Ave trail at Sunset Hills Rd |
To their credit, the VDOT rep suggested that the trail be opened until work started. That was almost a week ago and the trail was never opened and only today did we see any sign of work being done.
For people who parked in the lot called Reston North, they were trapped. Unless they caught a bus that stops in the lot, there was no legal way for them to cross the street. They couldn't reach the W&OD Trail because of the Trail Closed sign. They couldn't use the crosswalk because it was closed, and the crosswalk at the other end was under construction. We were assured that they all caught a bus. He must not have seen my wife who parked their the other day and crossed the street to catch the 505 bus.
There will be construction in this area for many months. If you can, I would avoid the intersection. From where I live near South Lakes HS I can reach the W&OD Trail using two other routes: South Lakes Dr to Sunrise Valley Dr to the W&OD Trail if I'm headed east, and South Lakes Dr to Pinecrest Dr to Glade Dr to the Fairfax Co Parkway trail to the W&OD Trail if I'm headed west.
About 10 years ago Supervisor Hudgins wrote a memo to county staff asking what procedures are in place to provide temporary access for pedestrians and bicyclists during construction. Apparently it's still a work in progress.
When FABB reps met with VDOT reps about closure of the Fairfax County Parkway trail, we asked for the following: That trail closures be treated like a road closure: Avoid if at all possible, provide a detour, close for as short a time as possible, provide advance notification, provide ongoing notification regarding status of the closure, and provide information about alternative routes if a detour is not provided. VDOT staff assured us that ped/bike detours are included in all new projects, even the smallest project. This is not a VDOT project.
Comstock has done a good job of providing pedestrian and bike access along the Wiehle Ave trail in front of their main construction site at the station. They need to do a better job at this intersection.
Update: Today (May 23) we rode by this intersection and saw this group of construction workers walking around the Trail Closed barrier and crossing in the close crosswalk. I believe they were headed to the Comstock development. One of the works actually walked into the sign when he looked back at his co-workers. They are a fine example to others on how to deal with the closed trail.
Labels: comstock, sunset hills road, vdot, wiehle ave, wiehle station