Tuesday, May 27, 2014
 

Fairfax Co Parkway Trail repairs update

Trail signs at Baron Cameron -
Note the page-size map (left)
and info (right) signs
Repaving of sections of the Parkway trail from Route 7 to New Dominion Parkway is complete. Large cracks in that section will be filled by another contractor who will begin work soon.

When working from Route 7 south the contractor was having to work against traffic which was causing delays. Even though the trail work was off road, the asphalt truck was using the shoulder of the Parkway. VDOT has decided to begin work at the southern end of phase one at Route 50, working north with traffic to New Dominion Parkway.

We heard from a cyclist who was concerned about the smoothness of the new asphalt patches. VDOT has agreed make sure the patches pass their smoothness tests.

Here is the schedule for work on the trail next week:
Fairfax County

Direction: Rte. 286 N/B Fairfax County Parkway.
Where:  From Rte. 50 to Stringfellow Road.
When: Tuesday 5/27/14 thru Friday 5/30/14 from 8:00 AM to 4:00 PM (weather permitting)
What: Temporary Bike Trail closure.
Why: Maintenance repairs.
Project0286-029-112, N501
Police: NO
Contact Info: Roy Leake: 540-860-2601
Emergency Contact: Sam Ghobadian: 571-722-5315

Labels:

Comments:

Post a Comment

Contact FABB via email: info@fabb-bikes.org

Subscribe to the
FABB e-newsletter


Subscribe to posts:
[Atom 1.0] or [RSS 2.0]





  Bike to Work Day 2015 at Wiehle Station

  Transportation choices

This page is powered by Blogger. Isn't yours?

Archives