W&OD Trail bridge over Beltway under construction
As you can tell from recent posts, there's a lot happening related to HOT lanes construction the Beltway. This is new from the Northern Virginia Regional Park Authority website:
The new W&OD Trail bridge over the Capital Beltway is under construction on the north side of the existing trail bridge. The existing bridge and trail will remain open during construction. Currently, on both sides of the Beltway, bridge abutment walls are being constructed next to the existing bridge and trail. PLEASE USE CAUTION WHILE IN THESE WORK ZONES. The bridge beams are scheduled to be installed in October and the bridge deck is scheduled to be installed in November. Once the new bridge is open to trail users, the existing bridge will be removed. Please check this site for updates.